Monday, December 8, 2008

Condo Reno Update (8th in a series)

Our condo renos are 80% complete now.

100% of all flooring, electrical wiring, light fixtures and dry-walling jobs are finished.

The ensuite plumbing (for the shower and tub) is complete and the vanity has been assembled and installed.

Outstanding jobs to complete:

Installation of kitchen cabinetry and built in appliances (scheduled for December 18)

Installation of the ensuite marble tub surround, backsplash and walk-out sills (marble is being cut to order now and should be installed before Xmas)

Installation of kitchen countertop: Ceasarstone surface has been selected and estimated but cannot be finally measured / templated for fabrication until after kitchen cabinets are installed.

Installation of kitchen backsplash: glass tiles have been ordered but cannot be installed until after cabinets and countertop are installed.

Installation of master/ensuite and shower glass panels/doors: have been measured and are being fabricated. Should be available for installation in two weeks.

Installation of shower kit: should be installed before glass panels/doors are installed

Relocation of granite countertop (from ensuite) and installation of new sink in 2nd bathroom: should be complete this week.

Installation of tub filler: should be installed after tub backsplash is installed.

Installation of new ensuite toilet: should be complete this week.

Completion of wall trim work (baseboard in closets is outstanding): should be complete this week.