Our condo renos are 80% complete now.
100% of all flooring, electrical wiring, light fixtures and dry-walling jobs are finished.
The ensuite plumbing (for the shower and tub) is complete and the vanity has been assembled and installed.
Outstanding jobs to complete:
Installation of kitchen cabinetry and built in appliances (scheduled for December 18)
Installation of the ensuite marble tub surround, backsplash and walk-out sills (marble is being cut to order now and should be installed before Xmas)
Installation of kitchen countertop: Ceasarstone surface has been selected and estimated but cannot be finally measured / templated for fabrication until after kitchen cabinets are installed.
Installation of kitchen backsplash: glass tiles have been ordered but cannot be installed until after cabinets and countertop are installed.
Installation of master/ensuite and shower glass panels/doors: have been measured and are being fabricated. Should be available for installation in two weeks.
Installation of shower kit: should be installed before glass panels/doors are installed
Relocation of granite countertop (from ensuite) and installation of new sink in 2nd bathroom: should be complete this week.
Installation of tub filler: should be installed after tub backsplash is installed.
Installation of new ensuite toilet: should be complete this week.
Completion of wall trim work (baseboard in closets is outstanding): should be complete this week.